The decisive task now facing striking miners is to stop coal and oil movements into the power stations. This is a very different question to the earlier attempt to hit steel production. The power industry is vital to every other sector of the economy—to cut power supplies is to cut production and disrupt everything else. That is understood by every miner and every other worker. It is the direct line to victory and will get an enthusiastic response. Power workers' jobs are not threatened by such action. They have none of the steel workers' fears about government plans to destroy their industry, or demoralisation over recent defeats. The decision of the TUC to black strikebreaking coal and oil movements gives the miners an important lever in seeking the co-operation of other workers. Steps must be taken now to turn these words into action. A combination of solidarity action by official approaches to the unions concerned and a determined attempt by the miners and other workers to stop scab lorries moving coal into vital power stations will ensure victory. In this full page feature PETE DICKINSON explains the situation in the power industry and pinpoints the key areas. Below he explains the facts behind NCB hypocrisy over pit damage. ELECTRICITY IS produced in Britain by generators in power stations powered by coal, oil, nuclear or hydroelectric means. A small number of gas fired plants exist to cope with peak demand.
All the electricity produced is pooled on a national basis by a grid of high voltage transmission lines and switching stations. (See diagram). This means that if demand is high in one part of the country or a power station in a particular area breaks down, electricity can be drawn from power stations in other areas to fill the gap.
The grid is not infinitely flexible however. Power can be transmitted only over a maximum of 60 miles, so a national network of power stations must always be kept in operation to avoid cuts in supply. Control and operation of the grid system is based on a national control centre in London and seven regional centres in Manchester, Leeds, Nottingham, Birmingham, St Albans, East Grinstead and Bristol. One of the problems faced by the CEGB is meeting peak demand for electricity. The diagram shows that demand for electricity at 4pm is double that at 6 am. To cover this situation small gas fired generators are used which can be started up quickly. Longer term variations in demand are met by keeping some power stations mothballed during the summer and bringing them 'on stream' during particularly cold spells in the winter.
Old oil fired stations are normally used for this, but during the strike they have been used flat out to cover 'base load' demand. Now that winter is approaching the CEGB will again have to make provision for peak loadings. Their 'flexibility' will be reduced to substitue oil for coal because large coal fired stations are the least suitable technically to cope with sudden peaks in demand.
### Output
concentrated The backbone of the National Grid is provided by the output of a relatively small number of huge power station complexes. The 400KV network is mainly supplied from stations in Yorkshire like Drax and Ferrybridge, the Trent Valley and those round Manchester. In fact, a network of about 15 stations in these areas provide nearly ⅔ the capacity of the national grid in normal times.
### SUMMER AND WINTER
SYSTEM 1972/3 AND GW Winter Day Typical 1972/3 Winter Day Since the strike began oil and nuclear stations have been producing 40% of electricity and coal fired stations in striking areas have been mothballed as reported in Militant previously. The top priority for the Tories has been to keep the large coal fired stations in the working or partly working areas of the Trent Valley fully operational.
The power stations Managemel Typical 1972/3 Summer Day Typ Sur Hours 1982/:
Day Notts coalfield are obviously top of the list. The big ones here are Ratcliffe, a few miles from Nottingham (the largest in the country, Cottam and West Burton near Retford. The majority of the coal produced and stockpiled in the Notts area since the strike began has been moved into these, and another few key stations, at first by rail but since June mainly by lorry.
The other key stations in partly working areas are Drakelow near Burton on Trent, Rugely and Ironbridge in Staffordshire and Fiddler's Ferry near Warrington. These few stations could have accounted for 70% of the 15GW capacity available from coal fired stations during the summer. (1 GW is 1000 million watts or the power of 1 million electric fires)
The stopping of coal movements into these stations would have an enormous effect on coal stocks because the CEGB would be forced to burn off the remaining stockpiles at stations where there is little possibility of replenishment, which could result in disruptions in the power supply within weeks.
At many of the power stations in the Trent Valley there are inadequate facilities for handling the coal delivered by road. This work is done mainly by GMBATU and T&G members working under difficult conditions and undoubtedly unhappy at handling scab coal delivered by road.
An approach now by the miners to the shop stewards of all unions in these stations is a vital necessity. In the light of the TUC decision to give full backing to the miners many stewards will give the NUM a sympathetic hearing and a positive reponse when the issues are explained.